Capital improvement, right-of-way and infrastructure projects

 

Project Description:

Under this project, 88th Avenue S./S. 218th Street will be widened to a three-lane roadway from 88th Avenue S. to 94th Place S.  Included in the project are:

  • New culvert over Garrison Creek along S. 218th Street
  • New curb, sidewalk, planter strip, widened shoulder
  • Overhead utilities moved underground
  • New storm drainage, and treatment and detention facility
  • Wetland mitigation

Timeline of Events:

Summer 2018 - Bid project
Summer 2018 - Start construction
Winter 2019 - Complete construction

 

Estimated Construction Cost:

$9,000,000

Project Engineers:

Stephen Lincoln
253-856-5552

Ken Langholz
253-856-5516

Contractor:

To be determined

Construction Inspector:

To be determined 

 

 